When is an Invitation for Bids (IFB) used?

  1. When requirements are vague and negotiable

  2. When requirements are clearly defined

  3. When accepting applications from professionals

  4. When seeking grant proposals

The correct answer is: When requirements are clearly defined

An Invitation for Bids (IFB) is used when requirements are clearly defined. This procurement method is ideal for scenarios where the purchasing agency knows exactly what they need, including detailed specifications, quantities, and delivery timelines. The process requires bidders to submit firm bids based on the specified requirements, allowing for a straightforward comparison of offers based on price and compliance with the stated specifications. In contrast, processes such as accepting applications from professionals or seeking grant proposals typically involve more subjective criteria, where qualifications or project outlines may play a larger role in the decision-making process. Additionally, using an IFB for vague or negotiable requirements would not be appropriate, as such situations call for different procurement methods that allow for discussion or modifications.